Blog Updates from the City of Decatur Engineering Department
August 25, 2019
						
						
The engineering department is working diligently to keep multiple projects moving forward throughout the city. These projects include:
- Austin High School Traffic Signal:
- Site assessments have taken place at the Austin High School Entrance on Modaus Road and plans for a traffic signal are underway.
 
 - Bibb Garrett Bridge:
- Plans have been drawn, are being evaluated and reviewed. Appraisals for right-of-way acquisition have begun.
 
 - Brookmeade Road & Country Club Road:
- Currently working on acquiring easements.
 
 - Carrie Matthews Center:
- Tests are being done to determine the cause of the structural instability of the interior foundation at the Carrie Matthews Center.
 - Tests are being conducted in a manner as to not disturb daily activities at the center.
 - Multiple courses of action are being considered in order to best fix the current state of the building.
 
 - Line Street & Ferry Street:
- Bids for Line Street and Ferry Street have been received.
 - The next step planned in this project is to go before council on September 3, 2019 to accept the bid.
 - Anticipate work to begin in October.
 
 - Modaus Road & Carrington Drive:
- Geotechnical testing has been conducted at the intersection of Modaus Road and Carrington Drive in efforts to design a new intersection configuration.
 - Enough design work will have been completed to have a good cost estimate by September 6, and full construction plans completed in October.
 
 - Paving:
- Lists for each council district have been selected and are awaiting budget approval. Work will begin at the beginning of the fiscal year.
 
 - Shady Grove Lane:
- We are awaiting easement and right-of-way acquisition.
 
 - Sidewalks:
- Multiple sidewalks and handicap ramps throughout the city are always being evaluated and updated to American’s with Disabilities Act Standards.
 
 - Spring Avenue:
- Utility relocation has been completed.
 - Paving is expected to begin near Vestavia Drive in the later part of this week.
 - Efforts are being made to work during times of least traffic congestion.
 
 - Upper River Road:
- Pre-Bid meeting will be held September 5, 2019.
 - Bid opening scheduled for September 17, 2019.
 
 
Again, the engineering department is working diligently to improve safety throughout our city. Patience is of the utmost importance.